[ARCHIVED] Main Street and 200 North Roadway Improvements

SR-273_ConstructionPostcard_August2024 (002)_Page_1

Main Street and 200 North Roadway Improvements Begin Week of Aug. 19

UDOT will begin roadway improvements next week along sections of 200 North and Main Street. The project includes:

  • US-89 bridge deck rehabilitation
  • Pedestrian ramp upgrades to meet ADA standards
  • Roadway signage updates
  • Intersection improvements at 100 N. and Center St.
  • Pavement resurfacing

Project completion is expected by late summer 2025, with a winter shut-down from late fall 2024 to late spring 2025.

For more specific schedule and impacts information, please visit udotinput.utah.gov/kays200main.

Schedule and Construction Impacts

August 19, 2024: Main St. Bridge over US-89 (near Cherry Hill)

  • Bridge deck rehabilitation is expected to take approx. six weeks.
  • Traffic will be reduced to one lane in each direction over the bridge.

August 19, 2024: Pedestrian Ramp and Roadway Signage Upgrades

  • Includes approx. 50 pedestrian sidewalk ramp upgrades at various intersections along Main St. and 200 N. to meet ADA standards.
  • Construction will require roadway shoulder and sidewalk closures.
  • Construction is expected to continue through early fall 2024.

September 2024: Main St. and 100 N. and Center St. Intersections

  • Includes construction of intersection bulb-outs on the west side of Main St./100 N. and on the east side of Main St./Center St.
  • This work will facilitate Kaysville’s conversion of 100 N. to one-way westbound between Main St. and 100 W. and Center St. to one-way eastbound from Main St. to 100 E.
  • 10-day side-street closures of 100 N. and Center St. will be in place.

Late Spring 2025: SR-273 (Main St. & 200 N.) Resurfacing

  • Paving will occur at night and will include lane closures.
  • Paving is expected to be complete by mid-summer 2025.

Also, as part of this project "Vision Main Street" 

Vision Main Street

"Vision Main Street" is a Kaysville City initiative to enhance Main Street, making it more appealing to both businesses and residents. In coordination with the UDOT project, the city plans to implement the following changes by late fall 2024 to increase parking in downtown Kaysville:

Center Street

  • Will be converted to a one-way street eastbound from Main Street to 100 East.
  • Will include 17 angled and 16 parallel parking stalls.

The city initially planned to convert 100 North into a one-way westbound street from Main Street to 100 West, adding angled and parallel parking. However, after receiving feedback from residents, the city has been working with its traffic engineering consultant to find a solution that effectively balances the interests of all stakeholders.

The proposed changes to 100 North were based on input from meetings held in 2021 and 2022 with Main Street businesses, who requested that the city explore ways to create additional on-street parking in the downtown area.

As resident feedback is being reviewed, construction on 100 North has been placed on hold, and no traffic changes will be made as part of the current UDOT project. However, UDOT will still proceed with work to improve sidewalk ADA curb ramps throughout the Main Street project, including at the intersection of 100 North and Main Street.

The city will provide further updates as the process continues.

If you have any questions related to this project, please contact the public involvement team at ebenson@langdongroupinc.com or (385) 493-0810.