Main Street and 200 North Roadway Improvements Begin Week of Aug. 19
UDOT will begin roadway improvements next week along sections of 200 North and Main Street. The project includes:
- US-89 bridge deck rehabilitation
- Pedestrian ramp upgrades to meet ADA standards
- Roadway signage updates
- Intersection improvements at 100 N. and Center St.
- Pavement resurfacing
Project completion is expected by late summer 2025, with a winter shut-down from late fall 2024 to late spring 2025.
For more specific schedule and impacts information, please visit udotinput.utah.gov/kays200main.
Schedule and Construction Impacts
August 19, 2024: Main St. Bridge over US-89 (near Cherry Hill)
- Bridge deck rehabilitation is expected to take approx. six weeks.
- Traffic will be reduced to one lane in each direction over the bridge.
August 19, 2024: Pedestrian Ramp and Roadway Signage Upgrades
- Includes approx. 50 pedestrian sidewalk ramp upgrades at various intersections along Main St. and 200 N. to meet ADA standards.
- Construction will require roadway shoulder and sidewalk closures.
- Construction is expected to continue through early fall 2024.
September 2024: Main St. and 100 N. and Center St. Intersections
- Includes construction of intersection bulb-outs on the west side of Main St./100 N. and on the east side of Main St./Center St.
- This work will facilitate Kaysville’s conversion of 100 N. to one-way westbound between Main St. and 100 W. and Center St. to one-way eastbound from Main St. to 100 E.
- 10-day side-street closures of 100 N. and Center St. will be in place.
Late Spring 2025: SR-273 (Main St. & 200 N.) Resurfacing
- Paving will occur at night and will include lane closures.
- Paving is expected to be complete by mid-summer 2025.
Also, as part of this project "Vision Main Street"